Fully Open Edge Cloud

[ONGOING] Maintenance: Sep, 9th 2022 11:00 GMT: Lille Office datacenter phase out

Rapid.Space Maintenance. Read the article for real time information.
  • Last Update:2022-09-12
  • Version:001
  • Language:en

12/09/2022: Decision to phase out the Lille office datacenter

The decision has been made to unplug all machines in the LIlle office so they will never come back online after the incident from Sep 9th.

This will be a good opportunity to test SlapOS resiliency. We will also gain electricity consumption in the office.

RapidSpace team will make sure that all resilient services that were running there are correctly moved to some other datacenters except if it was the main service that was hosted in Lille (in this case you will be in charge to do the takeover, RapidSpace team will just write you a ticket).

09/09/2022 11:00 GMT: Lille office internet down

On 09/09/2022 11:00 GMT, the main internet access of our Lille office went down. We still have some legacy machines running there with very old services and those services were thus down.

We decided to do nothing and wait for Internet to come back during the next few days.